2 Process-Overhead Cranes in a Nitrogen Fertilizer Warehouse

Reference reportDouble Girder Crane | Bulk Crane | Cranes

    Technical requirements

    Power supply for two Process-Overhead Bulk Cranes

    Material handling in a nitrogen fertilizer warehouse requires precision and safety. The two process-overhead cranes (Bulk Cranes) operate with a robust power system: Conductor Rails for main power, Cable Festoons for crane crabs, and Motor-Driven Cable Reels for the bucket. Cellular Buffers at the cranes enhance safety by absorbing energy on end-points of the respective track.

    Conductix-Wampfler delivered state-of-the-art energy supply solutions, ensuring optimal performance and long-term reliability.

    Used Products
    Technical Information

    Main Power Supply

    ProductConductor rail program 0812 (4 x 400 A)
    Track length144 m
    Specific featuresSystem incl. insulator and clamping shoe in Stainless Steel V4A finishing

    Power Supply for the Crab

    ProductFestoon system, Program 0325
    Track length28 m

    Power Supply for the Bucket

    Product2 Motorized Cable Reels
    Cable4x16 + 2x(4x1,5C)
    General information
    CountryCzech
    CityLovosice
    OperatorLOVOCHEMIE, a.s